Types of Billing in Construction
- BHADANIS QUANTITY SURVEYING ONLINE TRAINING INSTITUTE

- Apr 22
- 3 min read
1. Lump‑Sum (Fixed‑Price) Billing
Definition: A single total price agreed up front for the entire scope of work.Calculation: Contractor submits one comprehensive amount covering all materials, labour, plant, overheads and profit.Pros:
Budget certainty for client
Simplified invoicing and cash‑flow forecastingCons:
Risk of unforeseen costs falls on contractor
Change orders require formal variation billingUse Cases:
Well‑defined, low‑risk projects (e.g., small building works)
Projects with limited scope changes
2. Unit‑Rate Billing
Definition: Work items are measured and billed at pre‑agreed rates per unit (e.g., per m³ of concrete, per metre of piping).Calculation: Quantity measured on site × unit rate for each itemPros: Types of Billing in Construction
Flexibility for varying quantities
Transparent linkage between measurement and costCons:
Requires rigorous measurement and verification
Cost uncertainty if quantities deviate significantlyUse Cases:
Earthworks, road construction, bulk concrete pours
3. Re‑Measurement (Measurement‑Based) Billing
Definition: Similar to unit‑rate but with full re‑measurement of work actually performed before billing.Calculation: Post‑execution measurement of all work items × respective unit ratesPros:
Accurate reflection of actual work done
Fair to both client and contractor when quantities are uncertainCons:
Administrative burden of detailed measurement
Potential for measurement disputesUse Cases:
Complex civil works where initial quantities can’t be finalized
4. Cost‑Plus Percentage Billing
Definition: Contractor bills actual cost of work plus an agreed percentage fee.Calculation: (Direct costs + indirect costs) + agreed % marginPros:
Contractor reimbursed for every expense
Incentive to keep costs down if percentage is fixedCons:
Less budget certainty for client
Requires full transparency in cost reportingUse Cases:
Emergency works, pilot projects, or highly uncertain scopes
5. Time & Materials Billing
Definition: Labour and plant are billed at hourly/daily rates, plus materials at cost.Calculation: (Labour hours × labour rate) + (Plant hours × plant rate) + materials costPros:
Direct link between effort and billing
Simplifies billing for variable workloadsCons:
Client bears risk of low productivity
Needs timesheet and materials log controlsUse Cases:
Maintenance, small repairs, or specialist subcontract work
6. Progress (Interim) Billing
Definition: Periodic billing based on percentage of work completed or milestone achievements.Calculation: Agreed percentage of contract sum or milestones certified × contract pricePros:
Smoothes cash flow for both parties
Reflects true work progressCons:
Requires robust progress measurement and certification
Disputes can arise over percent complete vs. physical progressUse Cases:
Large projects spanning many months or years
7. Milestone Billing
Definition: Payment triggered by achievement of specific project milestones (e.g., foundation complete, roof on).Calculation: Fixed sums tied to each milestone, as per contract schedulePros:
Aligns payments with tangible deliverables
Encourages timely achievement of key stagesCons:
Milestone definitions must be crystal‑clear
Delay in a milestone delays cash flowUse Cases:
High‑value turnkey contracts, EPC projects
8. Retention & Final Account Billing
Definition: A portion (typically 5–10%) of each interim payment is retained to ensure defect rectification; released upon project close‑out. Final account reconciles all sums.Calculation: Retention withheld on each interim × contract sum; final release upon issuance of final certificatePros:
Provides client security against incomplete or defective work
Incentivizes contractor to close out punch‑list promptlyCons:
Impacts contractor cash flow until project close‑out
Final account negotiations can delay retention releaseUse Cases:
Standard practice across most construction contracts
Mastering Billing Methods
Each billing type requires strong skills in measurement, valuation, documentation and contract interpretation. To develop your expertise, explore Bhadanis Institute’s specialized programs in:
Quantity Surveying
Estimation & Costing
Billing Engineering
Tendering & Contracts Management
Planning Engineering
Construction Project Management
These courses will equip you to select and implement the optimal billing approach for projects across Gulf capitals and Indian cities.
Comments